December 11, 2018: 2nd meeting of Nefzaoua Permit technical and operating committee (Tunisia)

2nd meeting of Nefzaoua Permit technical and operating committee (Tunisia) - December 11, 2018

The 2nd meeting of the Technical and Operating Committees for the Nefzaoua Permit was held by The Entreprise Tunisienne d’Activités Pétrolières (ETAP) and YNG Energy on December 11, 2018 in Tunis (Tunisia).
   
During the 2nd Nefzaoua Exploration Permit TCM representatives of ETAP and YNG reviewed the Operator’s activities in 2018, the preliminary 2D seismic data interpretation results and discussed the ongoing preparation for the upcoming 3D seismic acquisition campaign. 

The Operating Committee approved the Nefzaoua Permit working program for 2019, which will include 2D seismic data reprocessing, completing G&G data interpretation and tendering for 3D seismic data acquisition.